⚡ NEC 220.82(B) & (C) Engine

Residential Electrical Load Calculator

Compute connected demand kVA and line amperage at 240V to verify 100A-to-200A service upgrade needs.

Instant Engine
sq ft
High-Draw Electrification Loads
Calculated NEC 220.82 Demand Summary 2026 Code Profile
Total Connected Demand 142.5 Amps 34.20 kVA @ 240V
Panel Utilization Ratio 142.5% Deficit on 100A Service
Recommended Service 200-Amp Class 200 Meter Enclosure
IRA Section 25C Credit Up to 30% Section 25C 26 U.S.C. § 25C(d)(2)(D)
🔒 Calculate Local Permit & Installation Rate
Verified Residential Electrical Dispatch

Speak With a Licensed Residential Electrical Estimator

Connect directly by telephone to review local municipal permit requirements, utility disconnect scheduling, and 200A service upgrade availability in your county.

Single-Family Residential Electrical Panel Upgrades Only
Have Your 5-Digit US ZIP Code & Calculated Demand Load Ready
Covers 100A-to-200A heavy-ups, FPE/Zinsco hazard replacements, and subpanel installations.
📞 Call Estimator: (833) 781-1701
Engineering Tool 7 min read 2026 NFPA 70 / NEC Standard

Dwelling Subpanel Sizing & Feeder Conductor Calculator

Calculate feeder breaker amperage, four-wire feeder conductor sizes, and isolated neutral bar configurations for detached garages, basements, ADUs, and workshop subpanels.

1. Feeder Sizing & 4-Wire Isolation Rules for Residential Subpanels

When a main 200-amp load center runs out of physical breaker slots—or when powering a detached garage, workshop, basement suite, or Accessory Dwelling Unit (ADU)—installing a 60A, 100A, or 125A feeder subpanel is the primary engineering solution. However, subpanel installations must comply with strict feeder ampacity (NEC Article 215/225) and neutral-ground isolation mandates (NEC 250.24(A)(5) and 250.32).

Unlike a main service panel where the neutral bus and equipment grounding bus are bonded together, a subpanel must maintain 100% electrical isolation between the neutral bar (floating) and the grounded metal enclosure. Mixing neutrals and grounds in a subpanel energizes metal conduits and equipment frames with return current.

Subpanel Feeder Amperage, Conductor Gauge & Voltage Drop Reference (240V)

Subpanel RatingCopper Feeder (75°C)Aluminum Feeder (75°C)Equipment Ground WireMax Run (<3% Voltage Drop)
60-Amp Subpanel 6 AWG Copper (4-Wire) 4 AWG Aluminum SER 10 AWG Copper Up to 110 Feet
90-Amp Subpanel 3 AWG Copper (4-Wire) 2 AWG Aluminum MHF/SER 8 AWG Copper Up to 135 Feet
100-Amp Subpanel 3 AWG Copper (4-Wire) 1 AWG Aluminum SER 8 AWG Copper Up to 150 Feet
125-Amp Subpanel 1 AWG Copper (4-Wire) 1/0 AWG Aluminum SER 6 AWG Copper Up to 175 Feet
150-Amp Subpanel 1/0 AWG Copper (4-Wire) 2/0 AWG Aluminum SER 6 AWG Copper Up to 200 Feet

2. Detached Structure Grounding Rods (NEC 250.32(A))

Whenever a feeder supplies a separate detached building (such as a detached garage, barn, or backyard ADU), NEC 250.32(A) requires establishing a local grounding electrode system at the detached building—typically two 8-foot driven ground rods spaced 6 feet apart—connected to the subpanel's isolated grounding bar, while keeping the neutral bar unbonded.

3. Does Adding a Subpanel Increase Total Home Amperage?

Adding a 100A subpanel to an existing 100A main panel adds physical breaker spaces but does not increase your home's total service capacity. If your NEC 220.82 total connected demand exceeds 100 amps, you must upgrade the main service entrance to 200 amps first.

Technical Questions & Code Clarifications

Why do detached garage subpanels require 4 wires plus ground rods?

The 4-wire feeder (Hot L1, Hot L2, Neutral, Equipment Ground) provides a low-impedance fault current path back to the main panel breaker so faults trip immediately, while the local ground rods dissipate lightning and atmospheric voltage gradients at the outbuilding.

Can I use 2-2-2-4 Aluminum Mobile Home Feeder (MHF) for a 100-amp subpanel?

No. Under NEC Table 310.16, 2 AWG aluminum is capped at 90 amps at the 75°C terminal column (unless the entire dwelling service is carried under 310.12, which does not apply to subpanels). A 2-2-2-4 Al feeder must be protected by a 90A breaker maximum.